I think back to when I sat for the PMP exam and remember taking the first few minutes to quickly write down the following formulas. It was my cheat sheet. There was enough to think about for the next few hours and worrying if I could remember some key formulas was not one of them. So, here is a bit of advice. If you're preparing[1] to take the PMP exam, MEMORIZE these formulas. The exam won't come right out and ask you to identify the correct formula for a variance of an activity. Rather, it will offer a question like: Your current activity was pessimistically estimated at 65 hours and optimistically estimated at 40 hours. What is the variance of the activity? (you can use this formula for both time and cost) You can see how knowing the formula is going to make you or break you on this question.
Do yourself a favor. Make flash cards, get a tattoo, it doesn't matter. Commit these formulas to memory and you'll save yourself some pain and suffering (and a few points on the exam).
The Formulas
Acronym
Title
Formula
PERT
Program Evaluation and Review Technique
P = Pessimistic Estimate M = Most Likely Estimate O = Optimistic Estimate
Standard Deviation of Activity
Variance of an Activity
Total Float
LS - ES or LF - EF
Communications Channels
[N(N-1)] / 2
CV
Cost Variance
EV - AC
SV
Schedule Variance
EV - PV
CPI
Cost Performance Index
EV / AC
SPI
Schedule Performance Index
EV / PV
EAC
Estimate at Completion
BAC / CPI
AC + ETC
AC + (BAC - EV)
ETC
Estimate to Complete
ETC = EAC - AC
VAC
Variance at Completion
BAC - EAC
CPI
c
Cumulative Cost Performance Index
Σ
EV /
Σ
AC
TCPI
To-Complete Performance Index